These resources were published in a Savannah Lakes Village announcement by Councilman Chuck Cook. The announcement states that County Auditor Clarissa Parks reviewed and verified the spreadsheets and accompanying information. The materials focus on SLV but may also be useful to property owners throughout McCormick County.
View the dedicated 2026 property-tax resource page →
Blank calculator →
Sample calculator →
Calculation table (PDF) →
Historical millage comparison →
Latest meeting records
South Carolina Data Center Community Protection Act
State Representative Daniel Gibson has introduced a proposed Data Center Community Protection Act. This is a draft legislative proposal, not enacted law. McCormick First is preserving the publicly circulated draft for informational review and will update this entry if an official legislative filing or revised version becomes available.
District Five superintendent finalists announced
Spartanburg County School District Five announced three finalists in its search for the next superintendent: Eric Williams, Assistant Superintendent for School Leadership with Greenville County Schools; Jason Johns, Superintendent of Anderson School District Two; and Dr. Jaime Hembree, Superintendent of McCormick County School District.
The district says the finalists will participate in upcoming public forums. Details are available from District Five at spart5.net/SuperintendentSearch2026.
October 15 Public Hearing on Ordinances 26-06, 26-08 and 26-05
McCormick County Council will hold a public hearing on Thursday, October 15, 2026, at 6:00 p.m. at the W.S. Mims Activity Center, 516 Mims Dr., McCormick, SC 29835.
Ordinance 26-06: An ordinance amending the McCormick County Zoning Ordinance (Ordinance 21-08) to impose restrictions on the location and development of data centers and emerging technology projects in McCormick County.
Ordinance 26-08: An ordinance amending the McCormick County Zoning Ordinance (Ordinance 21-08) and the McCormick County Zoning Map to change the zoning district designations for properties identified by Tax Map # 152-00-00-002, 152-00-00-003, and 127-08-02-003 from Forest Agriculture (FA) to Service/Industrial (SI).
Ordinance 26-05: An ordinance creating a special tax assessment for eligible rehabilitated historic properties.
Published notice reference: 222312 · 09/25/2026.
Ordinance 26-06 — Data Center and Emerging Technology Ordinance
The County has posted an updated version of Ordinance 26-06 ahead of the October 15 public hearing. This link points to the County’s current PDF source and should be treated as the controlling public copy available to residents at this time.
Special-Called County Council Meeting
1:00 p.m. at the Administration Center, 610 South Mine Street. The agenda lists executive session for contractual and personnel matters, legal advice, and Economic Development — SLV Windfall Group Novation and Modification Agreement. Council may take action on matters discussed in executive session.
Read McCormick First’s reported September 15 vote results →
Airport Environs Overlay District — Ordinance 22-20
The preserved PDF includes Ordinance 22-20 and its signed adoption page dated August 15, 2023, together with the Airport Environs Overlay District materials. The ordinance revises the temporary-uses table and Section 2.5 concerning airport protective areas.
This is the source copy retained by McCormick First. Consult the County for the current controlling ordinance, official map and any later amendments.
View airport ordinance and attachments (PDF) →
View the separately labeled approximate Project Palmetto overlay →
County Council Meeting at the Administration Center
6:00 p.m. at 610 South Mine Street. The agenda includes second readings of Ordinances 26-06, 26-08 and 26-05; millage; water-system services; public comments; and executive-session matters.
McCormick First Recording of Council Votes
Watch McCormick First’s approximately 15-minute recording of the votes in three consecutive parts, with MP4 downloads available. This community recording accompanies our meeting summary.
Watch the Council votes →The September 10 meeting has concluded. The agenda and notices below are preserved as meeting records. Read McCormick First’s account of the meeting and votes →
September 10 Meeting: Attendee Information
The County’s notice provides building and gym opening times, lobby sign-up instructions for Public Comment and the Public Hearing, attendance rules, and its YouTube livestream link.
View the County’s attendee notice →
Visit the County’s YouTube channel →
September 10 Rescheduled County Council Meeting
The official agenda schedules public comments; a public hearing and third reading on Ordinance 25-11; first reading, by title only, of a temporary nine-month data-center moratorium (Ordinance 26-07); first reading, by title only, of data-center and emerging-technology development restrictions (Ordinance 26-06); and first reading, by title only, of a separate three-parcel rezoning (Ordinance 26-08). It also lists other County business and a possible executive session.
September 10 Public Hearing on Ordinance 25-11
The Index-Journal published notice that McCormick County Council will hold a public hearing Thursday, September 10, 2026, at 6:00 p.m. at the W.S. Mims Activity Center, 516 Mims Drive. The notice identifies Ordinance 25-11, the proposed change from Forest Agriculture to Service/Industrial, and five affected parcels.
The County subsequently posted the complete agenda, which confirms the public hearing and third reading and identifies the additional matters scheduled for consideration.
SCELP Letter Concerning Ordinance 25-11
Attorney Emily S. Poole of the South Carolina Environmental Law Project sent this letter to McCormick County Attorney G.P. Callison concerning the public-hearing notice and the third reading that had been scheduled for August 18. The letter presents SCELP’s legal position and is not a court ruling or a County legal opinion.
McCormick County Council Regular Meeting
6:00 p.m. at the McCormick County Administration Center, 610 South Mine Street. Ordinance 25-11’s third reading was subsequently removed. Source: McCormick County Council.
View originally posted agenda as PDF →
Download original Word document →
Capital Project Sales Tax (CPST) Projects
A community member recently asked McCormick First about the status of projects being funded through McCormick County's voter-approved Capital Project Sales Tax (CPST), commonly referred to as the one-cent sales tax.
McCormick First contacted County Administrator James Upchurch and Crystal Barnes for an update.
Five projects in progress; three completed
The County's latest published CPST graphic reports:
- In progress: Projects #1, #3, #6, #7, and #8.
- Completed: Projects #2, #4, and #5.
- No status is shown: Projects #9 through #17.
This confirms that Project #6 is now in progress and shows Projects #7 and #8 underway as well. It also provides updated status for the earlier public-safety and fire-department projects.

Current status by project
#1 – Public Safety Communications Improvements
$516,420
Status: In progress.
#2 – Fire Department Ladder Truck
$400,000 · Sandy Branch
Status: Completed.
#3 – Fire Department Training Center
$575,000
Status: In progress.
#4 – Fire Department Tanker Truck
$400,000 · Parksville
Status: Completed.
#5 – Fire Department Construction Project
$33,000 · Clarks Hill
Status: Completed.
#6 – Fire Department Pumper Replacement
$260,000 · Clarks Hill
Status: In progress.
#7 – Fire Department Tanker Truck
$200,000 · Town of McCormick
Status: In progress.
#8 – Self-Contained Breathing Apparatus
$15,919.80 · Clarks Hill
Status: In progress.
About the CPST program
The voter-approved project list includes 17 projects totaling $7.3 million. The official funding agreement specifies that projects are to be funded in their approved order of priority using CPST revenue. It also provides that the County may issue bonds, with repayment coming from CPST revenues, to advance the approved projects.
The County previously advised McCormick First that it must have the full amount of funding available before beginning a project, that approximately $250,000 per quarter is being received in CPST revenue, and that Council has discussed possible bonding to move projects forward more quickly. The newly published status graphic should be treated as the current source for individual project status.
Official County information:
McCormick County CPST Projects page →
McCormick First will continue to share updates as additional projects move forward.
Document categories
Planning & Zoning
Rezoning applications, parcel information, staff materials, and Planning Commission records.
County Ordinances
Moratorium language, data center text amendments, readings, and adopted requirements.
Meeting Records
Official agendas, minutes, public notices, and supporting packets.
Maps & Technical Records
Site maps, utility information, environmental filings, and agency permits when available.
Document standards
Whenever possible, each file will include its source, publication date, and version. Drafts will be clearly marked.